1.Project Overview

This project is located in Malaysia and aims to address the increasingly severe freshwater shortage problem in local industrial areas and surrounding communities. The project adopts a highly integrated integrated container design, achieving rapid conversion from seawater to high-quality drinking water.

Project Name

Malaysia 200TPD seawater desalination container project

Project Type

Seawater Desalination

Project address

Malaysia

Project Launch

August 2022

Project Delivery

October 2022

Project Status

Delivered and operating stably

2. Project Background and Requirements

Although Malaysia belongs to a tropical rainforest climate with abundant rainfall, its unique geography and industrial structure bring special water use challenges:
Large industrial water shortage: The industrial zone where the project is located is expanding rapidly, and the existing water supply network cannot meet the surging industrial water demand.
Frequent seasonal water shortages: Affected by the El Ni ñ o phenomenon, Southeast Asia often faces seasonal droughts, which limit residents' access to domestic water.
Geographical limitations: Some coastal areas have low-lying terrain or are far away from the municipal main pipeline network, and the cost of laying long-distance water pipelines is extremely high and the cycle is long.
Therefore, the integrated seawater desalination solution of "on-site water intake and on-site treatment" has become the most efficient solution.
We provide a set of integrated container seawater desalination equipment with a capacity of 200 tons/day to address the aforementioned pain points.
Flexible deployment, plug and play:
The equipment adopts a standard container design, and all pipelines and circuits are prefabricated in the factory. After arriving at the site, there is no need for complex civil engineering, only the connection of inlet and outlet water pipelines and power supply is required to operate. This is also the key to the project being able to be quickly delivered and put into use within 2 months (2022.8-2022.10) .
Core process configuration:
The system core adopts SWRO-HR8040 seawater desalination membrane elements, with a total of 16 units configured. This model of membrane element has the characteristics of high flux and high desalination rate, specially designed for high salinity seawater, which can effectively resist biological and organic pollution, and is very suitable for the warm water environment along the coast of Malaysia.
After systematic treatment, the quality of raw water has been fundamentally improved, fully meeting industrial cooling and residential drinking standards.

3.Water quality comparison and economic benefits

Parameter

Raw water data

Filter water data

PH

4-5

6-7

SS(mg/L)

100

0

TDS(mg/L)

28000

400

Turbidity

≤ 1 NTU

Recovery rate

35-50%

Note: Complies with WHO drinking water standard.

Economic account (operating costs):
The expected operating cost of the project is controlled at 3.6-4.2 yuan/ton. Compared to long-distance water transportation or expensive industrial water outage losses, this cost is highly competitive, and there is still room for cost reduction with large-scale application.
Livelihood account (water supply guarantee):
This project not only serves industrial production, but also takes into account the water needs of surrounding residential communities. The produced water meets the drinking water standards of the World Health Organization (WHO), directly solving the problem of difficulty and high cost of drinking water for local residents, and improving the quality of life of the community.

Image display

Internal structure diagram of container

Internal structure diagram of container

Internal structure diagram of container

Internal structure diagram of container

Video Presentation
Case Feedback

Please provide the following valid information, and we will contact you as soon as possible

Other Cases
Low cost and efficient Bengbu 200TPD high ammonia nitrogen wastewater PTFE deamination project
Ultra high concentration ammonia nitrogen wastewater treatment project, a stable economic and technological solution to replace traditional physical and chemical methods
More
0.4-0.5 yuan/ton, Sichuan 400m ³/d ceramic flat membrane ultrafiltration integrated equipment project
The ceramic flat membrane project is a model of high difficulty and high wave water quality treatment, which can achieve significant economic benefits at extremely low operating costs.
More
A secondary seawater desalination system priced at 5.165 yuan/ton? The minimum cost can be controlled at 3 yuan
Zhoushan, Zhejiang, China produces 250 tons of seawater desalination system per day, with ultra-low operating costs and stable long-term performance.
More
120TPD Landfill Renovation Plan - Controlling Pollution and Costs
Customized solutions to address the issue of leachate in landfills, effectively controlling surrounding pollution and cost consumption.
More
Less than 2 yuan, 60 TPD integrated MBR project of Mount Huangshan Hospital
In view of the sewage treatment needs of Bengbu Mount Huangshan Hospital, we have designed a cost-effective integrated MBR treatment device
More
2 yuan/ton cost - Qatar factory integrated MBR equipment water reuse project
Qatar field project, stable operation and super cost-effectiveness
More
Extreme environment: Russia 1440m3/d water supply project, cost 3.5-4 yuan
This project is tailored to the extreme geographical environment of Russia, with customized design and installation of water filtration projects, and has extremely high economic value.
More
Malaysia 200TPD seawater desalination container project
A container seawater desalination system that can be delivered quickly, with stable operation and cost-effectiveness
More
200m ³/d to alleviate the freshwater crisis on islands, less than 4 yuan per ton of freshwater
Customized fresh water system of scenic island can effectively solve the problem of drinking difficulty and high cost for the public
More
Reclaimed water with a capacity of 1000TPD per day costs only about 2.5 yuan
The Anqing reclaimed water reuse project adopts a two-stage filtration process, achieving 1000TPD/day at a cost of only about 2.5 yuan
More
leo@coopmem.com
+86 15556910898
For More Cooperate Information